  1. Start the Abiquo upgrade to 5.3 as usual including
    1. Stop the Abiquo platform
    2. Create backups including snapshots, Database dump, and Redis dump
  2. Upgrade the database
  3. STOP the upgrade
  4. Run the PIM planner and obtain the migration plan


Run the PIM migrator

Do these steps to run the PIM migrator.

Warning

Before you run the PIM migrator on your production servers:

  1. you must run it in your lab environment
  2. you must run it in dry run mode with the migration plan from the PIM planner that you ran on a dump of your production database